C_TPLM22_67 · Question #89
If a component and the upper-level activity have different delivery information. Which of the following has priority for the component? Please choose the correct answer. Response:
The correct answer is A. Internal delivery information. See the full explanation below for the reasoning.
Question
If a component and the upper-level activity have different delivery information. Which of the following has priority for the component? Please choose the correct answer. Response:
Options
- AInternal delivery information
- BExternal delivery information
- COrder delivery information
- DMaterial delivery information
How the community answered
(40 responses)- A80% (32)
- B13% (5)
- C5% (2)
- D3% (1)