Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned? There are 3 correct answers to this question…

The correct answer is B. Positions C. Persons D. Organizational units. See the full explanation below for the reasoning.

Question

Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned? There are 3 correct answers to this question. Response:

Options

  • AJobs
  • BPositions
  • CPersons
  • DOrganizational units