nerdexam
SAP

C_TPLM22_67 · Question #82

You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network…

The correct answer is B. The scheduling type is set to capacity requirements only. See the full explanation below for the reasoning.

Question

You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason? Please choose the correct answer. Response:

Options

  • AThere is a loop in the network.
  • BThe scheduling type is set to capacity requirements only.
  • CThe control key is set to no scheduling.
  • DThe normal duration of each activity is missing.

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    76% (29)
  • C
    16% (6)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full C_TPLM22_67 Practice