Question
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason? Please choose the correct answer. Response:
Options
- AThere is a loop in the network.
- BThe scheduling type is set to capacity requirements only.
- CThe control key is set to no scheduling.
- DThe normal duration of each activity is missing.