C_TPLM22_67 · Question #78
While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled? Please choose the correct answer. Response:
The correct answer is D. Scheduling baseline, planned and forecast. See the full explanation below for the reasoning.
Question
While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled? Please choose the correct answer. Response:
Options
- AScheduling backwards
- BScheduling forwards
- CVariances
- DScheduling baseline, planned and forecast
How the community answered
(27 responses)- A19% (5)
- B7% (2)
- C4% (1)
- D70% (19)