Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile? Please choose the correct answer. Response:

The correct answer is D. Proj.summ.master data indicator. See the full explanation below for the reasoning.

Question

Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile? Please choose the correct answer. Response:

Options

  • AProject summarization indicator
  • BCapacity requirement indicator
  • CVersion profile indicator
  • DProj.summ.master data indicator

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    17% (8)
  • C
    7% (3)
  • D
    72% (33)