C_TPLM22_67 · Question #63
Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the…
The correct answer is C. Released D. Partially released. See the full explanation below for the reasoning.
Question
Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board. What is the status that must be set before you can enter actual start and actual end dates? There are 2 correct answers to this question. Response:
Options
- APartially finished
- BPartially set
- CReleased
- DPartially released
How the community answered
(49 responses)- A14% (7)
- B6% (3)
- C80% (39)