Which scheduling calculates the latest start and finish dates for all activities? Please choose the correct answer. Response:

The correct answer is A. Backward scheduling. See the full explanation below for the reasoning.

Question

Which scheduling calculates the latest start and finish dates for all activities? Please choose the correct answer. Response:

Options

  • ABackward scheduling
  • BForward scheduling
  • CProject based scheduling
  • DNetwork based scheduling

How the community answered

(49 responses)
  • A
    76% (37)
  • B
    12% (6)
  • C
    8% (4)
  • D
    4% (2)