Which scheduling calculates the latest start and finish dates for all activities? Please choose the correct answer. Response:
The correct answer is A. Backward scheduling. See the full explanation below for the reasoning.
Question
Which scheduling calculates the latest start and finish dates for all activities? Please choose the correct answer. Response:
Options
- ABackward scheduling
- BForward scheduling
- CProject based scheduling
- DNetwork based scheduling
How the community answered
(49 responses)- A76% (37)
- B12% (6)
- C8% (4)
- D4% (2)