SAP
C_TPLM22_67 · Question #188
Which of the following levels can you assign persons to work centers? There are 2 correct answers to this question. Response:
The correct answer is A. Work center level D. Capacity category level. See the full explanation below for the reasoning.
Question
Which of the following levels can you assign persons to work centers? There are 2 correct answers to this question. Response:
Options
- AWork center level
- BAssignment level
- CWorkforce planning level
- DCapacity category level
How the community answered
(37 responses)- A76% (28)
- B11% (4)
- C14% (5)
Community Discussion
No community discussion yet for this question.