C_TPLM22_67 · Question #179

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element? There are 2 correct answers to this question. Response:

The correct answer is C. Cost element. See the full explanation below for the reasoning.

Question

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element? There are 2 correct answers to this question. Response:

Options

  • ABilling element
  • BPricing element
  • CCost element
  • DAccount assignment element

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    4% (1)
  • C
    78% (18)
  • D
    4% (1)