SAP
C_TPLM22_67 · Question #175
How can material components be assigned to network activities? There are 3 correct answers to this question. Response:
The correct answer is A. By assigning them manually B. Using the Internet-based catalog E. Using the bill of materials transfer. See the full explanation below for the reasoning.
Question
How can material components be assigned to network activities? There are 3 correct answers to this question. Response:
Options
- ABy assigning them manually
- BUsing the Internet-based catalog
- CUsing assigned sales orders
- DUsing ProMan
- EUsing the bill of materials transfer
How the community answered
(53 responses)- A83% (44)
- C11% (6)
- D6% (3)
Community Discussion