You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose? Please choose the correct answer. Response:

The correct answer is D. Bottom-up. See the full explanation below for the reasoning.

Question

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose? Please choose the correct answer. Response:

Options

  • ATop-down
  • BFree planning
  • CStrict bottom-up
  • DBottom-up

How the community answered

(61 responses)
  • A
    3% (2)
  • B
    13% (8)
  • C
    5% (3)
  • D
    79% (48)

Community Discussion

No community discussion yet for this question.

Full C_TPLM22_67 Practice