You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose? Please choose the correct answer. Response:
The correct answer is D. Bottom-up. See the full explanation below for the reasoning.
Question
You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose? Please choose the correct answer. Response:
Options
- ATop-down
- BFree planning
- CStrict bottom-up
- DBottom-up
How the community answered
(61 responses)- A3% (2)
- B13% (8)
- C5% (3)
- D79% (48)