SAP
C_TPLM22_67 · Question #162
What should you call up to view all the information on an active or completed job that was scheduled in the scheduler in schedule manager? Please choose the correct answer. Response:
The correct answer is A. Monitor. See the full explanation below for the reasoning.
Question
What should you call up to view all the information on an active or completed job that was scheduled in the scheduler in schedule manager? Please choose the correct answer. Response:
Options
- AMonitor
- BMemory joggers
- CJob list
- DTask list
How the community answered
(60 responses)- A80% (48)
- B12% (7)
- C3% (2)
- D5% (3)
Community Discussion
No community discussion yet for this question.