C_TPLM22_67 · Question #126

In which of the following ways Open PS allows you to exchange data directly with MS project? There are 3 correct answers to this question. Response:

The correct answer is A. Create a project in MS project from an SAP PS project C. Reconcile data from a project in Microsoft Project with a project in SAP PS D. Transfer a project from MS project to SAP PS. See the full explanation below for the reasoning.

Question

In which of the following ways Open PS allows you to exchange data directly with MS project? There are 3 correct answers to this question. Response:

Options

  • ACreate a project in MS project from an SAP PS project
  • BDownload MS project and Upload to SAP PS
  • CReconcile data from a project in Microsoft Project with a project in SAP PS
  • DTransfer a project from MS project to SAP PS

How the community answered

(32 responses)
  • A
    72% (23)
  • B
    28% (9)