You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined. What are the possible reasons for…
The correct answer is A. A work center has not been assigned to the activity. B. The work center does not contain any available capacity data. See the full explanation below for the reasoning.
Question
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined. What are the possible reasons for this? There are 2 correct answers to this question. Response:
Options
- AA work center has not been assigned to the activity.
- BThe work center does not contain any available capacity data.
- CThe wrong activity type category is entered in the activity.
- DThe indicator calculate capacity requirements is deactivated in the header of the network.
How the community answered
(15 responses)- A73% (11)
- C20% (3)
- D7% (1)
Community Discussion