C_TPLM22_67 · Question #1120
With reference to Organization Assignments in Project Systems, which of the following statements are true? There are 2 correct answers to this question. Response:
The correct answer is C. Controlling Area & Company Code assignments is mandatory at Project Definition level. D. Currency can be changed Only if the controlling area does not allow different company code. See the full explanation below for the reasoning.
Question
With reference to Organization Assignments in Project Systems, which of the following statements are true? There are 2 correct answers to this question. Response:
Options
- AProfit center assignment is mandatory at Project Definition level.
- BBusiness area assignment is mandatory at Project Definition level.
- CControlling Area & Company Code assignments is mandatory at Project Definition level.
- DCurrency can be changed Only if the controlling area does not allow different company code
How the community answered
(32 responses)- A6% (2)
- B9% (3)
- C84% (27)