C_TIOG20_65 · Question #38

(Topic 6) What must you do before you can view a nomination item under the Vehicle Berth Assignment node of the Berth Planning Board?

The correct answer is B. Peg the nomination item. See the full explanation below for the reasoning.

Question

  • (Topic 6)

What must you do before you can view a nomination item under the Vehicle Berth Assignment node of the Berth Planning Board?

Options

  • APerform a vehicle compatibility check
  • BPeg the nomination item
  • CAssign a ship in 3-way pegging
  • DPerform a berth compatibility check

How the community answered

(44 responses)
  • A
    11% (5)
  • B
    80% (35)
  • C
    7% (3)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.