(Topic 4) What is the prerequisite for assigning a new material to a tank in use?

The correct answer is A. The stock in the tank is zero in all units of measure. See the full explanation below for the reasoning.

Question

  • (Topic 4)

What is the prerequisite for assigning a new material to a tank in use?

Options

  • AThe stock in the tank is zero in all units of measure.
  • BThe new material is in a different plant.
  • CThe new material is in the same unit of measure group.
  • DThe stock in the tank is corrected for gain and loss.