Which element is mandatory in daily work schedule configuration? Please choose the correct answer. Response:
The correct answer is D. Daily work schedule class. See the full explanation below for the reasoning.
Question
Which element is mandatory in daily work schedule configuration? Please choose the correct answer. Response:
Options
- ACore times
- BTolerance time
- CMinimum working time
- DDaily work schedule class
How the community answered
(42 responses)- A2% (1)
- B5% (2)
- C12% (5)
- D81% (34)