When would you use an existing work schedule rule as the basis for a part-time work schedule without additional configuration? Please choose the correct answer. Response:

The correct answer is B. Current schedulE.Monday-Thursday (10 hours) New schedulE.Monday - Thursday (6 hours). See the full explanation below for the reasoning.

Question

When would you use an existing work schedule rule as the basis for a part-time work schedule without additional configuration? Please choose the correct answer. Response:

Options

  • ACurrent schedulE.Monday-Thursday (8 hours) and Friday (4 hours) New schedulE.Monday -
  • BCurrent schedulE.Monday-Thursday (10 hours) New schedulE.Monday - Thursday (6 hours)
  • CCurrent schedulE.Monday-Thursday (9 hours) and Friday (4 hours) New schedulE.Monday -
  • DCurrent schedulE.Monday - Friday (8 hours) New schedulE.Monday, Wednesday, and Friday (8

How the community answered

(52 responses)
  • A
    6% (3)
  • B
    75% (39)
  • C
    4% (2)
  • D
    15% (8)