Some of your employees work fewer hours prior to public holidays. What is the most efficient way to ensure that employee time is handed correctly? Please choose the correct answer. Response:
The correct answer is A. Create a daily work schedule variant and assign the work schedule to the employees. See the full explanation below for the reasoning.
Question
Some of your employees work fewer hours prior to public holidays. What is the most efficient way to ensure that employee time is handed correctly? Please choose the correct answer. Response:
Options
- ACreate a daily work schedule variant and assign the work schedule to the employees
- BCreate an attendance type to be mass uploaded to the employees records
- CCreate a rule in the time evaluation schema
- DCreate a substitution infotype to be uploaded to the employees records
How the community answered
(23 responses)- A74% (17)
- B13% (3)
- C4% (1)
- D9% (2)
Community Discussion