A customer needs to assign different public holiday calendars in their work schedule configuration. To which part of the HR structure is the public holiday calendar assigned? Please choose the…

The correct answer is D. Enterprise structure. See the full explanation below for the reasoning.

Question

A customer needs to assign different public holiday calendars in their work schedule configuration. To which part of the HR structure is the public holiday calendar assigned? Please choose the correct answer. Response:

Options

  • AOrganizational structure
  • BPersonnel structure
  • CEmployee structure
  • DEnterprise structure

How the community answered

(33 responses)
  • A
    12% (4)
  • B
    3% (1)
  • C
    9% (3)
  • D
    76% (25)