When would you use an existing work schedule rule as the basis for a part-time work schedule without additional configuration?

The correct answer is B. Current schedulE. Monday-Thursday (10 hours) New schedulE. Monday - Thursday (6 hours). See the full explanation below for the reasoning.

Question

When would you use an existing work schedule rule as the basis for a part-time work schedule without additional configuration?

Options

  • ACurrent schedulE. Monday-Thursday (8 hours) and Friday (4 hours) New schedulE. Monday - Friday
  • BCurrent schedulE. Monday-Thursday (10 hours) New schedulE. Monday - Thursday (6 hours)
  • CCurrent schedulE. Monday-Thursday (9 hours) and Friday (4 hours) New schedulE. Monday - Friday
  • DCurrent schedulE. Monday - Friday (8 hours) New schedulE. Monday, Wednesday, and Friday (8 hours)

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    80% (16)
  • C
    5% (1)
  • D
    5% (1)