An employee works on an internal project for one month. For this period, his personnel costs must be charged to a different cost center but he must remain assigned to the same position in…

The correct answer is C. Maintain the cost center in IT0027 (Cost Distribution). See the full explanation below for the reasoning.

Question

An employee works on an internal project for one month. For this period, his personnel costs must be charged to a different cost center but he must remain assigned to the same position in Organizational Management (OM). What is the recommended approach?

Options

  • AAssign a new cost center to the position through IT1001 (Relationship).
  • BChange the cost center in IT0001 (Organizational Assignment).
  • CMaintain the cost center in IT0027 (Cost Distribution).
  • DChange the cost center in IT1018 (Cost Distribution).

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    14% (6)
  • C
    74% (31)
  • D
    7% (3)