A customer wants to ensure that average working hours per period on IT0008 are updated when planned working hours on IT0007 change. How can you achieve this?
The correct answer is C. Use a dynamic action to update IT0008. See the full explanation below for the reasoning.
Question
A customer wants to ensure that average working hours per period on IT0008 are updated when planned working hours on IT0007 change. How can you achieve this?
Options
- AConfigure feature SCHKZ to default updates on IT0008.
- BRun report RPU51000 to update IT0008.
- CUse a dynamic action to update IT0008.
- DUse fast entry to update IT0008.
How the community answered
(38 responses)- A13% (5)
- B5% (2)
- C74% (28)
- D8% (3)