Which of the following is a typical sequence of steps in a Purchase to Pay process?

The correct answer is C. Purchase requisition -> Purchase order -> Goods receipt -> Invoice verification -> Payment. See the full explanation below for the reasoning.

Question

Which of the following is a typical sequence of steps in a Purchase to Pay process?

Options

  • APurchase requisition -> Goods issue -> Purchase verification -> Invoice receipts -> Payment
  • BPurchase order -> Purchase requisition -> Goods receipt -> Invoice verification -> Payment
  • CPurchase requisition -> Purchase order -> Goods receipt -> Invoice verification -> Payment
  • DPurchase requisition -> Goods verification -> Purchase receipts -> Invoice receipts -> Payment

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    8% (4)
  • C
    77% (37)
  • D
    13% (6)

Community Discussion

No community discussion yet for this question.

Full C_TFIN52_67 Practice