nerdexam
SAP

C_TFIN22_67 · Question #92

An Automotive customer works with 600,000 material numbers in a multi-level production environment. The whole costing run takes several hours. Now they are simulating the impact of an alternative…

The correct answer is C. Assign a suitable transfer control strategy to the relevant costing variant in the IMG. See the full explanation below for the reasoning.

Question

An Automotive customer works with 600,000 material numbers in a multi-level production environment. The whole costing run takes several hours. Now they are simulating the impact of an alternative production setup, which uses the same raw materials and semi- finished products. What option would you recommend to significantly shorten the duration of the costing run?

Options

  • AUse the Schedule Manager to optimize the duration of the Costing Run.
  • BUse the easy cost planning function for simplified and accelerated costing.
  • CAssign a suitable transfer control strategy to the relevant costing variant in the IMG
  • DDefine a mixed costing strategy and maintain mixing ratios.

How the community answered

(34 responses)
  • A
    18% (6)
  • B
    9% (3)
  • C
    71% (24)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_67 Practice