Question

In variance calculation we are using actual costs as the control costs and planned costs as the target costs. Which target cost version we are using? Please choose the correct answer. Response:

Options

  • ATarget cost version 0-total variance
  • BTarget cost version 1-production variance
  • CTarget cost version 2-planning variance
  • DTarget cost version 3-production variance of the period