How is Work in Process (WIP) calculated on a product cost collector?
The correct answer is D. Based on target cost, depending on the valuation variant settings. See the full explanation below for the reasoning.
Question
How is Work in Process (WIP) calculated on a product cost collector?
Options
- ABased on the standard cost estimate, independent of the valuation variant settings.
- BBased on the target cost, depending on the order type settings.
- CBased on actual cost, depending on the order status.
- DBased on target cost, depending on the valuation variant settings.
How the community answered
(38 responses)- A5% (2)
- B11% (4)
- C3% (1)
- D82% (31)
Community Discussion