C_TFIN22_67 · Question #7
What data is retained when a material cost estimate with quantity structure is saved? There are 3 correct answers to this question. Response:
The correct answer is A. Itemization B. Log E. Cost component split. See the full explanation below for the reasoning.
Question
What data is retained when a material cost estimate with quantity structure is saved? There are 3 correct answers to this question. Response:
Options
- AItemization
- BLog
- CExtract
- DVariance categories
- ECost component split
How the community answered
(26 responses)- A73% (19)
- C8% (2)
- D19% (5)