C_TFIN22_67 · Question #7

What data is retained when a material cost estimate with quantity structure is saved? There are 3 correct answers to this question. Response:

The correct answer is A. Itemization B. Log E. Cost component split. See the full explanation below for the reasoning.

Question

What data is retained when a material cost estimate with quantity structure is saved? There are 3 correct answers to this question. Response:

Options

  • AItemization
  • BLog
  • CExtract
  • DVariance categories
  • ECost component split

How the community answered

(26 responses)
  • A
    73% (19)
  • C
    8% (2)
  • D
    19% (5)

Community Discussion

No community discussion yet for this question.