How is the preliminary costing of a production order calculated? Please choose the correct answer. Response:

The correct answer is A. The quantity structure in the production order is valuated by the costing variant settings. See the full explanation below for the reasoning.

Question

How is the preliminary costing of a production order calculated? Please choose the correct answer. Response:

Options

  • AThe quantity structure in the production order is valuated by the costing variant settings
  • BThe costs are determined by the cost estimate of a reference order.
  • CThe actual quantities are valuated with plan values.
  • DThe standard price cost estimate of the material master record is adjusted to the order quantity.

How the community answered

(34 responses)
  • A
    71% (24)
  • B
    9% (3)
  • C
    6% (2)
  • D
    15% (5)