nerdexam
SAP

C_TFIN22_67 · Question #249

A service company decides to implement Activity-Based Costing. They collect all process- related cost on ABC processes and want to allocate them periodically to their sales orders in Sales Order…

The correct answer is C. Template allocation technique. See the full explanation below for the reasoning.

Question

A service company decides to implement Activity-Based Costing. They collect all process- related cost on ABC processes and want to allocate them periodically to their sales orders in Sales Order Management. Which functionality do you implement?

Options

  • AProcess assessment cycles
  • BProcess settlement
  • CTemplate allocation technique
  • DIndirect process allocation

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    14% (3)
  • C
    71% (15)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_67 Practice