SAP
C_TFIN22_67 · Question #190
When settling an investment order for an unfinished asset, the customer, by law, needs to settle the order to an asset under construction (AuC). How can this be accomplished in the system?
The correct answer is D. Set up the investment profile to use the AuC of a certain asset class and assign it to the used. See the full explanation below for the reasoning.
Question
When settling an investment order for an unfinished asset, the customer, by law, needs to settle the order to an asset under construction (AuC). How can this be accomplished in the system?
Options
- ASet up an appropriate investment reason and a threshold for scale level and assign both to the
- BSet up an assessment cycle to allocate the costs of the investment order to the previously created
- CAssign a settlement rule to AuC directly to the position of the investment program.
- DSet up the investment profile to use the AuC of a certain asset class and assign it to the used
How the community answered
(60 responses)- A3% (2)
- B17% (10)
- C8% (5)
- D72% (43)
Community Discussion