SAP
C_TFIN22_67 · Question #164
Let say for a product there exists three production versions. There are steps required to create a mixed cost estimate. What are they? Please choose the correct answer. Response:
The correct answer is D. All the above. See the full explanation below for the reasoning.
Question
Let say for a product there exists three production versions. There are steps required to create a mixed cost estimate. What are they? Please choose the correct answer. Response:
Options
- ACreate procurement alternatives for each of the production version.
- BDefine mixing ratios for the procurement alternatives.
- CSelect the configured quantity structure type and execute a material cost estimate based on the
- DAll the above.
How the community answered
(34 responses)- A3% (1)
- B15% (5)
- C12% (4)
- D71% (24)
Community Discussion
No community discussion yet for this question.