C_TFIN22_67 · Question #16

You want to receive internal activities in the material cost estimate by using a routing. How do achieve this? Please choose the correct answer. Response:

The correct answer is C. Assign a cost center and its activities to the corresponding work center. See the full explanation below for the reasoning.

Question

You want to receive internal activities in the material cost estimate by using a routing. How do achieve this? Please choose the correct answer. Response:

Options

  • AAssign a cost element with type 43 (internal activity allocation) to the routing operation.
  • BAssign a cost center with category "production" to the routing operation.
  • CAssign a cost center and its activities to the corresponding work center.
  • DAssign a cost center and its activities directly to the routing header.

How the community answered

(45 responses)
  • A
    9% (4)
  • B
    11% (5)
  • C
    76% (34)
  • D
    4% (2)