The controlling department requires the production order variances to be settled to profitability analysis. How can you achieve this? There are 2 correct answers to this question. Response:
The correct answer is A. Set the Variances indicator in the settlement profile D. Assign a PA transfer structure to the settlement profile. See the full explanation below for the reasoning.
Question
The controlling department requires the production order variances to be settled to profitability analysis. How can you achieve this? There are 2 correct answers to this question. Response:
Options
- ASet the Variances indicator in the settlement profile
- BAssign an allocation structure to the settlement profile.
- CSet the To Be Settled in Full indicator in the settlement profile.
- DAssign a PA transfer structure to the settlement profile
How the community answered
(34 responses)- A74% (25)
- B9% (3)
- C18% (6)
Community Discussion