What are the requirements to create primary cost component splits? Please choose the correct answer. Response:

The correct answer is E. All the above. See the full explanation below for the reasoning.

Question

What are the requirements to create primary cost component splits? Please choose the correct answer. Response:

Options

  • AAssign a cost component structure in the CO version in cost center and process cost planning.
  • BDetermine the prices through planned price iteration.
  • CDefine a cost component structure for the primary cost component split of product cost planning.
  • DDefine a transfer structure for the transfer of cost components in cost centers and Activity-based-
  • EAll the above