What are the impacts on an S price controlled material when releasing a material cost estimate? (Choose two)

The correct answer is B. Existing stock is valuated with the new price. D. New standard price is set. See the full explanation below for the reasoning.

Question

What are the impacts on an S price controlled material when releasing a material cost estimate? (Choose two)

Options

  • APrevious material movements are revaluated.
  • BExisting stock is valuated with the new price.
  • CMoving average price is adjusted.
  • DNew standard price is set.