SAP
C_TFIN22_67 · Question #133
What is the prerequisite for sales order controlling?
The correct answer is A. The sales order item must have a cost object assigned by a requirement class. See the full explanation below for the reasoning.
Question
What is the prerequisite for sales order controlling?
Options
- AThe sales order item must have a cost object assigned by a requirement class.
- BThe cost object of the sales order item must be created manually in the sales order.
- CA product cost collector must be assigned to the sales order item.
- DA valuated customer order special stock must be assigned to the sales order item.
How the community answered
(19 responses)- A74% (14)
- B11% (2)
- C5% (1)
- D11% (2)
Community Discussion
No community discussion yet for this question.