You post goods to storage location A. You notice that documents are missing, so you decide that the goods should not be used any further for the time being. The missing documents turn up at a later…
The correct answer is B. Goods receipt - transfer posting - stock transfer. See the full explanation below for the reasoning.
Question
You post goods to storage location A. You notice that documents are missing, so you decide that the goods should not be used any further for the time being. The missing documents turn up at a later stage and you proceed with the respective posting. The goods are subsequently moved from storage location A to storage location B, which you also record in the system. In what sequence are the three goods movements carried out? Select the correct answer.
Options
- AGoods receipt - transfer posting - goods issue
- BGoods receipt - transfer posting - stock transfer
- CGoods receipt - stock transfer - transfer posting
- DGoods receipt - transfer order - goods issue
How the community answered
(58 responses)- A3% (2)
- B83% (48)
- C9% (5)
- D5% (3)