A customer is producing materials according to planned independent requirements. At what time during the make-to-stock process is the requirement consumption of a new sales order item visible in the…
The correct answer is D. After a new planning run. See the full explanation below for the reasoning.
Question
A customer is producing materials according to planned independent requirements. At what time during the make-to-stock process is the requirement consumption of a new sales order item visible in the system?
Options
- AAfter creating the delivery
- BAfter posting goods issue
- CAfter saving the order
- DAfter a new planning run
How the community answered
(23 responses)- A4% (1)
- B9% (2)
- C13% (3)
- D74% (17)