nerdexam
SAP

C_TFIN22_66 · Question #54

What is the correct sequence of the ASAP methodology phases?

The correct answer is C. Project Preparation -> Business Blueprint -> Realization -> Final Preparation -> Go Live. See the full explanation below for the reasoning.

Question

What is the correct sequence of the ASAP methodology phases?

Options

  • AProject Preparation -> Business Blueprint -> Realization -> Training -> Go Live Support ->
  • BProject Launch -> Requirements and Design -> Build -> Go Live -> Run -> Optimization
  • CProject Preparation -> Business Blueprint -> Realization -> Final Preparation -> Go Live
  • DPlan Project -> Design Solution -> Build Solution -> Test -> Hand Over to IT -> Operate

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    81% (30)
  • D
    11% (4)

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_66 Practice