SAP
C_TFIN22_66 · Question #51
An Automotive customer works with 600,000 material numbers in a multi-level production environment. The whole costing run takes several hours. Now they are simulating the impact of an alternative…
The correct answer is C. Assign a suitable transfer control strategy to the relevant costing variant in the IMG. See the full explanation below for the reasoning.
Question
An Automotive customer works with 600,000 material numbers in a multi-level production environment. The whole costing run takes several hours. Now they are simulating the impact of an alternative production setup, which uses the same raw materials and semi-finished products. What option would you recommend to significantly shorten the duration of the costing run?
Options
- AUse the Schedule Manager to optimize the duration of the Costing Run.
- BUse the easy cost planning function for simplified and accelerated costing.
- CAssign a suitable transfer control strategy to the relevant costing variant in the IMG
- DDefine a mixed costing strategy and maintain mixing ratios.
How the community answered
(39 responses)- A13% (5)
- B5% (2)
- C79% (31)
- D3% (1)
Community Discussion
No community discussion yet for this question.