SAP
C_TFIN22_66 · Question #41
The system does not allow you to create a primary cost element. What do you check first?
The correct answer is A. Whether the P/L account exists. See the full explanation below for the reasoning.
Question
The system does not allow you to create a primary cost element. What do you check first?
Options
- AWhether the P/L account exists
- BWhether the cost element category is valid
- CWhether the balance sheet account exists
- DWhether the 6/L account currency is the same as the controlling area currency
How the community answered
(25 responses)- A80% (20)
- B8% (2)
- C8% (2)
- D4% (1)
Community Discussion
No community discussion yet for this question.