C_TFIN22_66 · Question #142
C_TFIN22_66 Question #142: Real Exam Question with Answer & Explanation
Sign in or unlock C_TFIN22_66 to reveal the answer and full explanation for question #142. The question stem and answer options stay visible for context.
Question
A company creates a cost center-related purchase order and complains that the commitment is not visible in the current commitment report, although commitment management is properly setup in CO. What is a possible reason?
Options
- ACommitment relevance is not activated in the relevant vendor master record.
- BCommitments are not posted real-time, but with a periodic transaction.
- CCommitment relevance is not activated in the relevant material master record.
- DThe commitment is already posted, but only visible in the report of the future period based