Question

A company creates a cost center-related purchase order and complains that the commitment is not visible in the current commitment report, although commitment management is properly setup in CO. What is a possible reason?

Options

  • ACommitment relevance is not activated in the relevant vendor master record.
  • BCommitments are not posted real-time, but with a periodic transaction.
  • CCommitment relevance is not activated in the relevant material master record.
  • DThe commitment is already posted, but only visible in the report of the future period based

Unlock C_TFIN22_66 to see the answer

You've previewed enough free C_TFIN22_66 questions. Unlock C_TFIN22_66 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.