The correct answer is A. In the controlling area. See the full explanation below for the reasoning.
Question
Where do you have to activate commitment management to enable postings of commitments on cost centers?
Options
- AIn the controlling area
- BIn the cost element master record
- CIn the cost center master record
- DIn the standard hierarchy