nerdexam
SAP

C_TFIN22_65 · Question #17

What are the prerequisites to calculate overhead costs on an internal order? Note: There are 2 correct answers to this question.

The correct answer is C. Define a costing sheet. D. Assign the costing sheet in the order master data. To calculate overhead costs on an internal order, a costing sheet must first be defined and then assigned to the specific order's master data.

Internal Orders

Question

What are the prerequisites to calculate overhead costs on an internal order? Note: There are 2 correct answers to this question.

Options

  • AAssign the costing sheet to the costing variant.
  • BDefine an overhead key.
  • CDefine a costing sheet.
  • DAssign the costing sheet in the order master data.

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    94% (30)

Why each option

To calculate overhead costs on an internal order, a costing sheet must first be defined and then assigned to the specific order's master data.

AAssign the costing sheet to the costing variant.

Assigning a costing sheet to a costing variant is relevant for product costing or project costing, not directly for calculating overheads on internal orders where the costing sheet is assigned in the order master.

BDefine an overhead key.

An overhead key is an optional field that allows for different overhead rates within a single costing sheet, but defining the overhead key itself is not a prerequisite for calculating overheads; the costing sheet is the fundamental prerequisite.

CDefine a costing sheet.Correct

Defining a costing sheet is essential because it contains the rules, percentages, and conditions for how overhead rates are calculated and applied to costs, forming the basis of overhead calculation.

DAssign the costing sheet in the order master data.Correct

Assigning the defined costing sheet directly in the internal order's master data links the specific order to the overhead calculation rules, enabling the system to apply overheads to the costs posted on that order.

Concept tested: Internal order overhead calculation setup

Topics

#Overhead calculation#Internal orders#Costing sheet#Order master data

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_65 Practice