How can you set up a valuation based on a cost estimate in costing-based profitability analysis? Note: There are 3 correct answers to this question.

The correct answer is C. By assigning the costing key to products. D. By assigning the costing key to material types. E. By assigning the costing variant in the costing key. See the full explanation below for the reasoning.

Question

How can you set up a valuation based on a cost estimate in costing-based profitability analysis? Note: There are 3 correct answers to this question.

Options

  • ABy assigning the costing variant to valuation variant.
  • BBy assigning the costing key to value fields.
  • CBy assigning the costing key to products.
  • DBy assigning the costing key to material types.
  • EBy assigning the costing variant in the costing key.

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    16% (5)
  • C
    77% (24)

Community Discussion