How do you receive the internal activities in the material cost estimate using a logistic quantity structure?

The correct answer is B. Assign a cost center and its activities in the work center of the routing operation. See the full explanation below for the reasoning.

Question

How do you receive the internal activities in the material cost estimate using a logistic quantity structure?

Options

  • AAssign the responsible cost center and its activities directly to the routing header.
  • BAssign a cost center and its activities in the work center of the routing operation.
  • CAssign a cost element with type 43 (internal activity allocation) to the routing operation.
  • DAssign a cost center and its activities to the bill of material.

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    77% (37)
  • C
    13% (6)
  • D
    6% (3)