Which of the following is a typical sequence of steps in a Purchase to Pay process?

The correct answer is A. Purchase requisition -> Purchase order -> Goods receipt -> Invoice verification Payment. See the full explanation below for the reasoning.

Question

Which of the following is a typical sequence of steps in a Purchase to Pay process?

Options

  • APurchase requisition -> Purchase order -> Goods receipt -> Invoice verification Payment
  • BPurchase requisition -> Goods issue -> Purchase verification -> Invoice receipts Payment
  • CPurchase requisition -> Goods verification -> Purchase receipts -> Invoice receipts Payment
  • DPurchase order -> Purchase requisition -> Goods receipt -> Invoice verification Payment

How the community answered

(27 responses)
  • A
    70% (19)
  • B
    11% (3)
  • C
    4% (1)
  • D
    15% (4)