SAP
C_TFIN22_64 · Question #5
Which data do you need to set up an accrual calculation with the percentage method? Note: There are 2 correct answers to this question.
The correct answer is C. Primary cost element (category 3) as accrual cost element. E. Cost center or internal order (order category 2) as credit object. See the full explanation below for the reasoning.
Question
Which data do you need to set up an accrual calculation with the percentage method? Note:
There are 2 correct answers to this question.
Options
- AAccrual settlement rules with percentage method.
- BSecondary cost element (category 31) as accrual cost element.
- CPrimary cost element (category 3) as accrual cost element.
- DAccrual allocation cycle with sender receiver segments.
- ECost center or internal order (order category 2) as credit object.
How the community answered
(29 responses)- A3% (1)
- B7% (2)
- C76% (22)
- D14% (4)
Community Discussion
No community discussion yet for this question.